 |
Septic
Design and Master Site Plan of Polifuncional Calama School
Santa
Cruz, Bolivia
(resumens de
los informes en Espaņol
(PDF)
Melissa
Trahan, Civil Engineering
Mary Anderson, Environmental Engineering
Kasey Cornwell, Environmental Engineering
International
Senior Design, CE 4990 & 4905
August 2005 |
 |
The
Project Background
In 2001, Michigan
Technological University (MTU) sent groups of students to developing
countries as part of a flagship International Senior Design Class
(ISD). Most recently, in the summer of 2005, two groups of students
traveled to Santa Cruz Bolivia.
LSS Engineering was among these students. They chose two schools
to evaluate, Polifuncional Calama in UV 125 and Oscar Ungaza de
la Vega in UV 127. Upon further analysis and scrutiny of the toilet
room and septic system problems, the project was narrowed down to
include only Calama. This decision was made after interviewing school
staff and students.
|

(1) LSS interviewing
Calama Director Anivar Rocha.
|
Calama
History:
Calama was founded on
March 23 in 1992. Initially there were only 140 students in 5 classrooms.
The students attend school in half-day turns including an evening
secession for adults. At present a total of 2200 students attend
school throughout the day. There are a total of 16 existing classrooms,
the Calama Director would like to add 4 additional rooms. The existing
septic system is the same one that was installed when the school
was founded.
|

(2) Calama school
yard, facing the stage. |

(3) Watching
water table soil boring. |

(4) Calama toilet
room with visible upwelling around building.

(5) Standing
water on toilet room floor. |
The
Trouble With Calama
Site
Exploration:
Site analysis
revealed standing water in and around the toilet rooms. The water
was assumed to be upwelling from the existing septic system and
runoff from the toilet room floors. The septic tank fills so fast
that it needs to be pumped every three months. When the school can’t
afford it themselves the parents pay for it. To slow the filling
of the tank the water to the toilets is turned off and they are
flushed manually when necessary. This allows the toilets to fill
with human waste.
Site Testing:
The tables below outline
the results from site analysis and testing. Water testing supported
assumptions that the puddles on the ground around the toilet room
contained human waste. Soil analysis through boring proved that
the site was comprised primarily of clay. The water table was found
to be located at 120 cm below the surface.
|

(6) Septic upwelling
along student walkway. |

(7) septic up
welling at base of toilet room. |

(8) Septic upwelling
along student walkway. |

(9) Collecting
a soil sample from the soil auger. |

(10) Water
testing results, light brown color shows presence of coliforms,
indicating human waste contamination.

|

(11) Surveying
at Camala |


|
The
Master Site Plan
The current
and future site plans for Calama can be seen to the left. Changes
made to the current design include:
Completion
of brick area in front of stage.
Additional classrooms
New location for bathrooms
New septic system
Study area
Volleyball pit
|
The
Possible Solutions |


|
Traditional
Bolivian System
The Traditional
Bolivian System consists of three parts in the following order:
a sedimentation tank, septic tank (camera septica), and dry well
(pozo ciego) and is currently being used. The system is failing
because the soil surrounding the dry well is not permeable enough
to handle the school’s wastewater load and the septic tank
cannot not be pumped as frequently as necessary due to lack of funds.
|


|
Holding
Tank
The Holding
Tank alternative is comprised of a large sedimentation tank which
acts as a holding tank, needing to be pumped at designated intervals.
Though a holding tank would overcome the problem of soil permeability
at Calama, this is not a feasible option due to the large maintenance
costs.
|


|
Subsurface
wetland
The Subsurface
Wetland alternative consists of a sedimentation tank and constructed
subsurface wetland and performs the same functions as a traditional
system. This is a feasible design for Calama, however it is limited
by cost of materials and land availability on site. Off site there
is enough land available but the ownership is unknown.
|




|
The
Recommended Solution
The recommended
design is one which utilizes a sand filter. The system will be gravity
fed and will run the wastewater effluent through two parallel septic
tanks before being dosed on the sand filter by a siphon. The filter
effluent will be collected in an underdrain and will need to be
piped to an existing ditch just beyond the Calama site walls to
the east. The effluent will have an approximate pathogen removal
of 99%, and secondary BOD5 and TSS removal to compliment that accomplished
in the septic tanks. The sand filter will be open at the top and
therefore it was recommended that a fence be used to keep students
from playing in it.
The sand filter
design accommodates 30% growth over the next 10 years. If the sand
filter is properly maintained it is possible for it to have a life
of up to 20 years. Backwash pipes have been included to allow for
periodic cleaning of the system.
Although the
sand filter is more costly to build then a traditional Bolivian
system, it will be more cost effective in the long run because the
traditional system will need to be pumped every few weeks. Also
it has been recommended that the school and community push to have
their location incorporated into Santa Cruz, sanitary sewer system.
The city supplies water to the school and legally for this reason
they should be removing the water as well. See the tables above
for system advantages and disadvantages and a cost analysis comparison
|
 |
The
Community Connections
While visiting
Calama, LSS made connections with faculty, students and community
members. Although none extended their welcome with as much enthusiasm
as the current senior class. Pictured with LSS to the immediate
left. As part of their senior gift to the school they were working
to beautify the school yard. This included planting flower beds,
organizing an open air study area and sand volleyball court. They
worked with LSS to incorporate their ideas into a master site plan
seen to the far left.
LSS also met with parents and staff who discussed their dedication
to helping make Calama a better place for the students. They even
committed to helping with the construction of the new septic system.
|
|
|