
Map
Team members:
Andrew Kelsch, Civil Engineer
Anthony Moraska, Environmental Engineer
Noah Mundt, Environmental Engineer
|
Gravity Fed Aqueduct System, International
Senior Design, Dominican Republic
CE 4905 Senior
Design Summer 2004
Slide Show Scenes of 2004 Projects
Introduction
The International Senior Design Class of 2004 was presented with the task
of designing a gravity fed aqueduct system for the village of Los Conucos.
Working with the current Master’s International Peace Corps student
on location, two weeks were spent designing the system which will be constructed
pending his final approval. Design objectives included the pipe layout,
spring box design, tap stand location and design, and the necessary calculations
to ensure the system will run under all the limiting factors. The major
design constraints included maneuvering the pipe network through the rugged
terrain of the area, and modeling the pipe diameters in order to supply
the tap stands with sufficient flow, taking into consideration the variable
changes in elevation.
|
Background
The city of
El Cercado is located approximately 25 kilometers from the Haitian border.
The village of Los Concucos, which is the site of this design project,
is positioned approximately 16 kilometers to the northwest of El Cercado,
at an elevation of 800 meters above sea level.
Ten families live
in Los Conucos, with 30 to 40 people inhabiting the village on a consistent
year round basis. This system is designed to adequately supply each of
these families with the allotted amount of 10 gallons of water per person
per day.
|
Survey and
Route Selection
PVC pipes will be
used for the distribution lines of the system, with exception to any gorge
crossings, areas where pipes will be exposed, or buried above the minimum
desired depth, for breakage protection purposes. Areas where these problems
occurred were avoided during the survey due to increased cost of galvanized
pipe. One gorge crossing was unavoidable, and designed to span the shortest
possible route for cost effectiveness. Illustrated by survey, changes
in the ground elevation required varying pipe diameters in order to maintain
enough pressure for the hydraulic grade line to remain above ground elevations.
This is crucial in gravity fed systems in order to maintain sufficient
pressure.
Pipes should be placed at a depth equal to or greater than 3 ft. Problems
encountered during the pipeline excavation may include:
Rocky ground that cannot be
penetrated by the tools available
Trees that must be avoided
due to laws prohibiting the cutting of living trees
Farmers fields that may be
affected by the construction process could invariably have an adverse
affect on the health of the family by destroying crops
Large gorges that should be
avoided if possible to keep costs down
Housing units along the system
that must remain
Existing irrigation ditches
that must remain undisturbed for future use in crop irrigation
Fences around enclosures where
livestock are held
|

Water Testing Results
|
Water Testing Results
Water testing was
done on the spring in Los Conucos to determine the level of bacterial
contamination of the spring. This was accomplished through the use of
Total Coliform/E. Coli (TC/EC) 3-M Petrifilms containing Violet Red Bile
(VBR) nutrients which indicate the presence, and an indicator that facilitates
colony enumeration, to enable a count of total coliforms and Escherichia
Coli bacteria present. The results (right) show the growth of one coliform
colony (Los Conucos 2) of the two inoculated Petrilms prepared.
Recommendations
Certain disinfection techniques may be used as simple and inexpensive
ways to treat the water. It should be noted that these methods are not
recommended for general or regular use if at all possible.
Emergency Disinfection
Measures:
Boiling – First
clear the water by letting it settle and filter through a clean cloth.
Boil the water vigorously for one full minute; boiling will kill all bacteria.
Overboiling, however, can concentrate chemical impurities such as nitrates.
Chlorine Bleach –
Add 10 drops of chlorine bleach to one quart of water, mix the treated
water thoroughly and let it stand for 30 minutes. If the water does not
have a slight chlorine odor, repeat the dosage and allow it to stand for
another 15 minutes. If the water tastes too strongly of chlorine, expose
it to the air for a few hours or pour it from one container to another
several times (www.bea.uga.edu).
|
Gorge Crossing
|
Pipeline
Layout
|
 Water Collection
|
EPANET
EPANET is the computer program which was used to simulate the hydraulic
behavior in this system. Altering the demand requirements at each tapstand
enabled the calculation of the maximum flow available when all tapstands
are open. In addition, this illustrated that the tapstands must be restricted
to a flow of .75 gpm as a safeguard when all the tapstands are open at the
same time. |
Summary
and Conclusions
The finalized design
for the water distribution to the village of Los Conucos is a gravity
fed system. The water from the spring will be harnessed into the system
by means of the designed spring box. Through the properties of gravity,
the water will be distributed though the system of pipes having diameters
of 1, 1.5, and 2 inches. The flow through the pipes will be sufficient
to supply 10 tap stand locations with water simultaneously for a period
of ____minutes with.
The time frame for
installation of this system is contingent upon the approval of Lyle Stone,
and the commitment of a local work force or an International Senior Design
Team. The completion of the system will follow the outlined work schedule
and cost approximately $4,480. Upon completion, this system will supply
ten families, and improve the quality of life of the women and children
who currently walk in upwards of 2 miles multiple times everyday in order
to supply their families with water.
|
Cost Analysis
|
|
|
|
Michigan Technological
University
Department of Civil and Environmental Engineering
1400 Townsend Drive
Houghton, Michigan, 49931 - 1295, USA
Department Phone: 1-906-487-2520
Department Fax: 1-906-487-2943
Department E-mail: cee@mtu.edu
© 2004 Michigan Technological University
The sale or commercial use of Illustrations, photographs and graphic images
presented on this site is not permitted. Educational uses are permitted,
provided credit is given to sources.
|
|